Отчет о строительных работах на объекте Индустриальный парк "Металлургический"

Report on construction work at the site of the Industrial Park, "Metallurgical"

Отчет о строительных работах на объекте Индустриальный парк "Металлургический" Отчет о строительных работах на объекте Индустриальный парк "Металлургический" Отчет о строительных работах на объекте Индустриальный парк "Металлургический" Отчет о строительных работах на объекте Индустриальный парк "Металлургический" Отчет о строительных работах на объекте Индустриальный парк "Металлургический"
A report on the implementation of works on construction of transformer substation "Metallurgical" step 1



the



the



the



the



the



the



the



the



the



the



the



the



the



the



the



the



the



the



the



the



the



the



the



the





 description                   

 Description of work performed 

 Box

 

 the Foundations

52 foundations-drenched 49

Preparing to fill the remaining 3 foundations (designed pits, poured footing)

Completed waterproofing of poured foundations

Work is underway to backfill foundations

Completed work on the removal of the developed soil   

     Frame

There are only 33колонны (36 columns and 16 stands Fachwerk)

Set links and struts columns axis And

Brought on the object 2 farm

On the trade contractor performed work for the production of half-timbered stands and crane girders, trusses, beams of the roof

     Roof

Brought on the object of prof sheet for roofing (report 24.06)

     Wall

 

     Windows

 

     Door/gate

 

     Floors

The tendering process for the device of floors (summarizing of the tender results this week week)

     External communication

 

     water

     tests fire hydrants pad forces Izhvodokanal

     sewage

     Conducted a visual inspection of the condition of the sewage system of the platform forces Izhvodokanal

     the stormwater Drainage

 

     Pipeline

     preparation of the contract design and the gasket. The works July-August

     al.supply

     Received the connection from the KPC power is 100kW 

     Internal communications

 

     water 

 

     sewage

 

     heating

    Contract for the supply of "Thermals" on the approval

     al.supply

 

     Landscaping

 

     Interior trim

 

     OTHERS

 

     Foundations phase II

     Summing-up of the tender for the installation of foundations




Share object in the social. networks:
Меню сайта